New Building Update: January 19, 2026
Construction Progress and Updates
- Electrical service is wired in basement but no power from overhead lines yet. DTE is scheduled to connect the lines the week of January 19th. (correction from last update)
- Window installation is complete.
- Main door installation is complete.
- Planned to complete side and rear doors next week (week of January 19th).
Committee Tasks
- TLN has been contacted to coordinate building electrical and data wiring. Follow-ups will continue to coordinate additional conduit and raceways needed for library operations.
- Need to provide inner wall bracing height to contractor for shelve installation bracing.
- Coordinate transportation of reclaimed doors once building is fully sealed in with masonry and windows.
- Work with South East Commercial on interior finishes.
- Review potential options for exterior signage on the building (“Addison Township Public Library” sign) shown below.