New Building Update :: 9/16/2025
Construction Progress
– Exterior rough framing completed. Interior framing to start once roof is complete and building sealed (windows/doors)
– Truss and Roof construction complete.
– Staircase for basement installed and concrete steps poured.
– Non-engraved bricks for building are ordered and planned to begin exterior masonry in about 4-5 weeks. Working though bids to select contractor. Exterior brick selection is available for review.
– Engraved bricks have been ordered.
– Roof sheeting complete and shingling is expected to start next week (Sep. 22nd)
– Building exterior for siding and windows trim in progress. Expected to complete by end of next week.
– Working on securing source for Windows/doors. (selection and delivery in next 4weeks)
– Power Line installation date note yet planned. Working on securing electrician.
– Plumbing contractor is secured. Will begin work after roof completed.
– Continued site work and piping will go over next few weeks.
Committee Tasks
– TLN has been contacted to coordinate building electrical and data wiring with TLN. Follow-ups will continue to coordinate additional conduit and raceways needed for library operations.
– Need to provide inner wall bracing height to contractor for shelve installation bracing.
– Reclaimed doors have been reviewed by the contractor. Doors in good shape and will be used for interior doors.
– Work with South East Commercial on interior finishes.
– Review potential options for exterior signage on the building (“Addison Township Public
Library” sign) shown below.
CONSTRUCTION UPDATE: We have a floor!
Crews were onsite today pouring the first floor. They’ll be back tomorrow to pour the basement.
Brick sales end on August 31. Get yours today before it’s too late.
CONSTRUCTION UPDATE: Backfilling the Site
Crews are onsite this week moving fill and bringing in fill to go around the basement walls.
- Facing the front of the building
- SW Corner
- Looking into the basement
CONSTRUCTION UPDATE: We Have Forms
Crews were onsite over the past week installing the forms for the basement walls. Concrete is expected to be poured in the next few days.
Once the walls are poured, the concrete will need to site for at least 10-days to cure. Once cured, the forms will be removed and back-fill pushed into and around the foundation.
It’s really starting to look like a Library.
Libraries Need Solid Foundations
Crews were on site this past week and have poured the footings for the new Library.
The Library will have a full basement, 5,000 sq ft, used primarly for storage. This new space will allow us to cancel our current storage unit.