CONSTRUCTION UPDATE: Backfilling the Site
Crews are onsite this week moving fill and bringing in fill to go around the basement walls.
- Facing the front of the building
- SW Corner
- Looking into the basement
CONSTRUCTION UPDATE: We Have Forms
Crews were onsite over the past week installing the forms for the basement walls. Concrete is expected to be poured in the next few days.
Once the walls are poured, the concrete will need to site for at least 10-days to cure. Once cured, the forms will be removed and back-fill pushed into and around the foundation.
It’s really starting to look like a Library.
Libraries Need Solid Foundations
Crews were on site this past week and have poured the footings for the new Library.
The Library will have a full basement, 5,000 sq ft, used primarly for storage. This new space will allow us to cancel our current storage unit.
CONSTRUCTION UPDATE, The Diggers are Here!
FOR IMMEDIATE RELEASE: May 23, 2025
The staking crew was out last week and this week the digging crew came on-site.
Last week the building, parking lot, septic field and other outside areas were staked out in prep for the diggers.
Diggers were out this week starting on the basement and building footings.
LIBRARY CONSTRUCTION HAS BEGUN
FOR IMMEDIATE RELEASE: May 14, 2025
Update Regarding Library Construction
- Bulldozers showed up on May 13 and have begun site preparation.
- The new Library will be located at 900 Lakeville Rd.

| Addison Township Library Board of Trustees 1400 Rochester Rd. Leonard, MI 48367 www.letsbuildalibrary.org |