New Building Update :: 9/16/2025

Construction Progress
– Exterior rough framing completed. Interior framing to start once roof is complete and building sealed (windows/doors)
– Truss and Roof construction complete.
– Staircase for basement installed and concrete steps poured.
– Non-engraved bricks for building are ordered and planned to begin exterior masonry in about 4-5 weeks. Working though bids to select contractor. Exterior brick selection is available for review.
– Engraved bricks have been ordered.
– Roof sheeting complete and shingling is expected to start next week (Sep. 22nd)
– Building exterior for siding and windows trim in progress. Expected to complete by end of next week.
– Working on securing source for Windows/doors. (selection and delivery in next 4weeks)
– Power Line installation date note yet planned. Working on securing electrician.
– Plumbing contractor is secured. Will begin work after roof completed.
– Continued site work and piping will go over next few weeks.

Committee Tasks
– TLN has been contacted to coordinate building electrical and data wiring with TLN. Follow-ups will continue to coordinate additional conduit and raceways needed for library operations.
– Need to provide inner wall bracing height to contractor for shelve installation bracing.
– Reclaimed doors have been reviewed by the contractor. Doors in good shape and will be used for interior doors.
– Work with South East Commercial on interior finishes.
– Review potential options for exterior signage on the building (“Addison Township Public
Library” sign) shown below.