New Building Update: January 19, 2026

Construction Progress and Updates

  • Electrical service is wired in basement but no power from overhead lines yet. DTE is scheduled to connect the lines the week of January 19th. (correction from last update)
  • Window installation is complete.
  • Main door installation is complete.
  • Planned to complete side and rear doors next week (week of January 19th).

 

Committee Tasks

  • TLN has been contacted to coordinate building electrical and data wiring. Follow-ups will continue to coordinate additional conduit and raceways needed for library operations.
  • Need to provide inner wall bracing height to contractor for shelve installation bracing.
  • Coordinate transportation of reclaimed doors once building is fully sealed in with masonry and windows.
  • Work with South East Commercial on interior finishes.
  • Review potential options for exterior signage on the building (“Addison Township Public Library” sign) shown below.

 