New Building Update: October 23, 2025
Construction Progress
- Septic is installed and inspections have been completed with approval.
- Engraved bricks for building have arrived. Non-engraved bricks are due to arrive next week (around 10/28/2025).
- Roofing is complete.
- Underground culverts installed and inspections have been completed with approval.
- Overflow structure for retention pond has been installed (Riser, Base and flow piping). Inspections completed and approved.
- Underground conduit for electrical and communication wires from over head lines have been installed (parking lot lights, potential future sign, main line into building and extra conduit for communication lines)
- Building exterior trim complete. Shop drawings for windows have been reviewed by contractor and approved. Windows ordered and due to be installed mid-November.
- Material for interior walls has been delivered on site.
- Currently planning the installation of gas line.
- After gas line installation, drive approach and first stage of parking lot paving will begin.