New Building Update: June 16, 2026

- Construction Progress and Updates
- Engraved bricks installed. Pilar caps will be picked up this week.
- Mechanical, Electrical and Plumbing plans still waiting approval from Township. Southeast Commercial has contacted an engineering resource to complete needed drawings.
- Well has been installed. Need to complete cleaning a testing process for full well approval.
- Construction of dumpster enclosure complete.
- Final site grading will begin.
- Parking lot lines and parking bumpers installed.
- Requirements for egress in the basement have been provided. 3 window wells will be installed. See image below for installation areas under review. Final location will be determined but 50ft access requirement.