New Building Update: August 18, 2026


Construction Progress and Updates

  • Front pillars with engraved bricks have been completed. (some minor cracking in mortar has
    been observed, repairs will be made)
  • All plans for Mechanical, Electrical and Plumbing have been completed and provided to the
    Township. Have approval to proceed.
  • HVAC equipment has been ordered. Contractor is asking for a down payment, expect invoice.
    Planning for HVAC equipment to arrive next week.
  • Final site grading will follow immediately after the rear patio is installed.
  • Egress window installation in progress, 3 of 4 have been installed.
    • Underground conduit for parking lot lighting was interfering with north east egress
      window. Conduit was re-routed to accommodate egress window installation. (~$2k)
  • Low-voltage (communication wiring) can be installed at this time. TLN will be consulted and help
    with coordinating installation.

 