New Building Update: August 18, 2026

Construction Progress and Updates
- Front pillars with engraved bricks have been completed. (some minor cracking in mortar has
been observed, repairs will be made) - All plans for Mechanical, Electrical and Plumbing have been completed and provided to the
Township. Have approval to proceed. - HVAC equipment has been ordered. Contractor is asking for a down payment, expect invoice.
Planning for HVAC equipment to arrive next week. - Final site grading will follow immediately after the rear patio is installed.
- Egress window installation in progress, 3 of 4 have been installed.
- Underground conduit for parking lot lighting was interfering with north east egress
window. Conduit was re-routed to accommodate egress window installation. (~$2k)
- Underground conduit for parking lot lighting was interfering with north east egress
- Low-voltage (communication wiring) can be installed at this time. TLN will be consulted and help
with coordinating installation.