From the community. For the community.

In The News

1 2 3 7

CONSTRUCTION UPDATE: We Have Forms

Crews were onsite over the past week installing the forms for the basement walls.  Concrete is expected to be poured in the next few days.

Once the walls are poured, the concrete will need to site for at least 10-days to cure.  Once cured, the forms will be removed and back-fill pushed into and around the foundation.

It’s really starting to look like a Library.

 

 

 

CONSTRUCTION UPDATE, The Diggers are Here!

FOR IMMEDIATE RELEASE: May 23, 2025

The staking crew was out last week and this week the digging crew came on-site.

Last week the building, parking lot, septic field and other outside areas were staked out in prep for the diggers.

Diggers were out this week starting on the basement and building footings.

1 2 3 7